hi.
i have tried to do the following:
creating a Finish Milestone (called FINISH) with a Mandatory Finish with its only Predecessor another Milestone (PROJECTED FINISH). the idea is that the FINISH activity would never fluctuate while the PROJECTED FINISH would show the project Float.
the problem is that it will NOT show the Longest Path except when the project falls behind.
is there a setting or something that could make it work?
thank you.