Hello,
I have just updated a plan with new start and finish dates.
On one activity i have changed the start date but i'm unable to change the finish date to the new required date. The new finish date is just 2 days more so i changed the duration by 2 but that didn't give me the required date.
Any suggestions please
Thanks
Richard