Dear All,
Good day!
Just want to ask about this query which happend to me lately.
I have made a Resources Loaded Schedule (BOQ Items as resources, which in turn will give me Total Budget Cost). I export it and import it to another computer. It shows a different Total Budget Cost in the new PC. I found out that some activities only have 1 resource while it should be more than 1. The difference can be traced to activities with multiple resources of the same resource. I mean, same resource added multiple times to the same activity but different Budgeted Units. Only 1 resource is imported to the other PC, what happen to the rest of the resources? Does this happen to P6 v.7? Anybody who can shere some info would highly be appreciate. Thanks.