Dear All
Currently I am handling a project having a one month delay ,I want to prepare man power histogram , The histogram i prepared is based on Baseline and now it is not reflecting the exact situation of site due to delay
1. Is it possible tp prepare a Histogram based on Actual start and expected to finish, or Expected to start or Expected to Finish?( I am using P3 as a software )
2.While preparing this, is there any need to remove Target program?
thanks