Hi All,
We got a new project and the client ask to prepare progress report and claim base on the manhours.
I think is not right cause the contract to them is lump sum re-measurement. I have proposed to them the progress report and claim base from installed qty, but they don't agree they still ask to submit manhours. any advise
Regards