Hi
The normal form of splitting activities is to use the 'Suspend' and 'Resume' functions in P6. However I find that this does not work in my P6 system.
The activity does not indicate a stop and restart date in my Gantt chart.
Is there something I am doing wrong.
Any help will be greatly appreciated
Thanks