Dear All planners...
In p6 The mystery of Units/Time⦠I been reviewing the all articles written about this issue and it not been agreed yet on one answer. So, I just want to be clear about this issue and I need direct and clear answer so, everybody can get it.
What is:
- Default Units/Time.. is it the number of hours every single resource work? Like 8 hrs/day
- Units/Time: is it the number of resources working for the activity like 5 engineers?
- Max units/Time: is it the max number of resources * Default units/Time ? ex (5)engineers * 8hrs/day= 40 ??
Thank you all,,
HANSON