I am referring to the Mike part of reply to my previous post
"..........This is based on the principle that if there is no BOQ item to price then the obligation is not included in the contract price....." .
I have case where certain items are not priced in B.o.Q but are covered in specification.As per the condition of sub contract ,specification take precedence to other documents.
Am I justified in arguing that what is not priced in B.o.Q is not my scope ?
Rgds