Hi,
I assigned a baseline with progress to the current project.The baseline update is one month before the current project.
I want to show progress bar on baseline.
1.I want to show baseline progress percent complete in the current project.That is two bars are there.One is current bar with current progress and baseline bar.I want to show baseline progress bar.
2.Show current progress on the baseline bar.
Schedule percent complete bar is not as baseline percent complete.I dont want to show schedule percent complete.
Urgent help please.
kp