Hi,
As we all know out of sequence activities create heaps of problems. For instance, remaining duration for out of sequence activities showing wrong because reaming early start is wrong (Due to activity being out of sequence).
I am looking for an UDf to call up a column for CURRENT DATE & later on use that as a global change representing correct remaining duration but I haven’t seen current date option anywhere in p6.
I appreciate hints in advance
Cheers,