Dear fellow planners,
I would like to get your background on how you are using "Schedule logs" created after calculation.
I mean, there is a lot of interesting information in it like errors or warnings (Activities w/o pred, w/o succ, with invalid relationship,...).
Firstly, this is a good report to clean some hidden mistakes but:
- Do you use it for other purpose (like claim, internal analyse,...) ?
- Do you compare rate of relationship Qty to Activities ? What is telling you that a schedule is not linked or too much ?
- ...
Well, if anyone has good idea on how to fully use this report, I will appreciate to get your feedback,
regards