Morning,
I am trying to change the resource in my plan to a different one. ie I have two resources define, Electrical 1 & Electrical 2.
All the activities with electrical 1 assigned i want to change that resource to electrical 2.
I created a refelction and tested it out and it when it changes the resource it also halves the Budget at Completion.
Any help greatly appreciated.
Dave