Dear All
Please suggest/provide your inputs for the above subject.
I want monitor resources of a bunch of activities with using LOE activity.
My Case : When updating the project if i realize that project is delayed due to client/employer and still i want to finish it on time and for that i need to mobilize additional resources.
What will be the Best Combination of DURATION TYPE & % COMPLETION TYPE for the LOE activity?
Please reply with your suggestion.
Regards,
Birju