Schedule % Completed to generate S Curve
Hi ..there is question , I am creating an Baseline S curve ....One way is take a resource assignment spread , Cumulate this & generate s curve ...Second way I have schedule % comelete , I run schedule with differance of 7 days form Project start date to Project complation ..Get % value figure then Cumulate this & generate s curve ....Now My question is Which is a correct way , I am using physical % complete ...