After creating the baseline of the schedule, I have generated a variance report of the current schedule against the baseline. I can see some variances on some activities, especially on activities that have some progress. Also, I can see the difference on the Gannt chart (they are supposed to be the same bar -plan vs current- after creating the baseline of the project, but they aren't, especially the ones that have some progress). Anyone knows why this is happening? Thank you in advance.