Hello Every one,
I am a planning engineer for 15.6 KM Road project which consists of 4 Tunnels and 3 Bridges. This project is being executed in a hilly terrain. This project started way back in 2006. This project is being plagued with problems. Around 2km of road is in land acquisition problems. Rest of the portion is completed. Recently one of the tunnel front portal collapsed since it's residing on man made debris. So we are waiting for an alternative design. I am actually trying to prepare a work program for this project. I am just not getting the idea about where to start. Do you want me to prepare a schedule with some said dates and change the dates once the problems get cleared. Please help me on this!!!!