Hi All,
In my schedule there are some resources showing over-Allocation.I want to perform resource levelling.The issue is that i am not able to sort out a method to separate the activities that have resources over allocated.For example,mason is Overallocated and is shown in Red in "Resource usage progile" for the month of december.Now i know that in December my Resource is overallocated.but how to filter out the relevent activities because i shall need total float values for resource levelling.
Regards,