Hi:
My question is that, does Max Unit/Time link with any thing?
I am using
Max Units/Time = 2h/d
Price/Unit = 12/d
Default Units/Time = 8h/d
Duration = 10d
This gives me Budgeted Units = duration x Default Units/Time = 10h/d x 8d = 80h
When I assign this to activity with 10d duration the
laboure Cost comes with = Budgeted Units x Price/Unit = 80h x $12/h = $960 (for 10 days)
But where is Max Unit/Time which 2h/d ? Does this not link with any thing? Or my calculations are wrong?