hai,
I have a recovery program and the activities have some actual start dates. The activity duration type assigned is fixed duration and units.
Resources assignments have - Preserve units, duration and units/times assigned.
but when i check the resource usage spread sheet, in updated activities, the Actual units + remaining units doesnt match to budgeted units. i have assigned resources as budgeted units.
Can anybody help me out
regards
ajeej