Good Morning Every One
I have a very simple querry for you guys
Let assume
Activity Duration Resource Duration
A 20 160hr (Put any resource )
Than in go on General tab make %comp type to physical .Now in start the activity give some physical percentage
Put 10 hours in actual f9 for 1st week
On second week Give some %com to physicalPut 40 hours in actual
f9 for 2nd week
When you check the activity spread sheet it show you 20 hours in last two weeks equally distributed
But we have done only 10 hours in first week and 30 hours in 2nd week
Any suggestions