Hi Guys
my % complete schedule and performance in my activity table varies from my % complete schedule and performance
in my wbs chart view if i add the two mentioned %'s in die chart blocks
why is this ? its using the same project and data ? im missing something here ....
EDIT, just figured it out while typing
the activity table has a filter that takes out level of effort activities, the chart doesnt
so my question now .... how do i add a filter in the chart view of the wbs ?