Guys ,
I developed the construction baseline Program/schedule/plan... and accordingly i prepared the % weightage plan.
progress reporting sheet, S curve etc. I show my progress in S curve.
Due to delay in my milestone dates i need to revise my Baseline and accordingly i will prepare the progress.
My question is:
In last week report to my client i showd the progress with some figures with overall progress as 54%
This week since my baseline is revised all the figures have been changed and overall progress is now 45% (bcz most of the dates have been pushed).
Is it acceptable if i show my revised progress with overall progress as 45%?
what will be the justification?
Just need to confirm and clear my self.