Hi,
can some one comment on how to display "Baseline % Complete" for activities as well as being summed up for the WBS levels as well.
the project is currently 50% into progress and "scheduled % complete" values are not the same as the ones that i had initially calculated for the scurve from baseline.
Schedule%complete gives rescheduled values not the baseline values as i understand????
Regards