Since a couple of weeks all the project I open, when I add a constraint to start on or after date+ 0:00 after scheduling it uses the last previous time liek 08:00 or something. Calendar is set to 24/7 and I can start the activity at any given time (even 0:01) except at 0:00.
Anyone know whether I'm doing something wrong or is this a bug? Version is Primavera 6.2 build 00001274
Regards,