i have created a p3 schedule with 250 activities
the schedule is currently set to duration in days
the problem is there are 3 times during the project where a shutdown must occur and you have a 6 hour max window to complete all tasks
so our activities look like this:
shutdown
weld beam
install new valve
change pc controller
restart plant
since these items must be done in succession i want to do: shutdown (o days) - weld beam (2 hours) - install new valve (2 hours) - change pc controller (2 hours) - restart plant (0 days)
the question is how can you mix days and hours in the schedule
since a day is defined as 8 hours and you know a certain task will take 2 hours can you input .25 days ?