Are we entitle to charge LD to Contractor based on the following :
- Natural of contract ( Infra structure work - 2.2km of main road , land scape , 2 bridges )
- Contract completion 15 August
- due to employer delay in the negotiation of the Electricity incoming line along main road( by authority) (3) months extension being granted till 15 November
- activities which will be delayed due to the late negotiation , main road , subgrade, crusherrun , binder and wearing course and some landscaping work along main road.
- on the other hand contractor also unable to complete the work by 15 august for other work not related to the above delay event.
Question :
As Employer , are we able to charge LD to the contractor for the portion of work which not affected by the employer delay event ???