Hi,
I have two tasks, Task A and Task B. Task A starts on 1/Sep/2011 and Task B starts on 1/Dec/2011. Task A's Finish is dependent on Task A's start i.e. it finishes 20 days (exact) after Task B starts. In case Task B's start date moves to say 15/Dec/2011, Task A's finish should automatically move to reflect the new finish date.
How do I represent this relationship in MS project?
Thank you
Arif