Dear All,
It is to my understanding that P6 is calculating OD of summary bars by using Planned Dates. I have tried to equate planned dates to current dates by using global change but at this time P6 is changing OD of In Progress activities.
Is there any way to set current dates as a calculation base of summary bars' original duration?
BR,
Baris Hazar