Regarding loading the schedule with cost what happens when updating that the actual cost is keeping changed for the nearly ended monthes i think becouse if there is an activity where its duration is is extended beyound its original duration so the program is re-distributing the money again on the new forcasted duration my question is is there any possible way where can i fix the money for the passed duration and only re- distribute on the remening duration only without changing the actual???