Hi All:
I am involved in a shutdown project and where have encountered the case detailed below
- The Activity Duration is 132Hrs (12Hrs x 11 shifts) & each shift is different with different mix of resource requirements.
- Please note that I have delinked the option to calculate activity duration basing on resource assignments (Edit-User preferences-Calculations)
- After the resources are assigned as below as per the respective calendars, I find that the resource budgeted/planned hours are not being allocated shift wise rather it is distributed to the entire duration of the Activity from start to finish.
Kindly advise how to solve this case.
Time scale (Day/Shift) | Start 5/05/2011 | 6/05/2011 | 7/05/2011 | 8/05/2011 | 9/05/2011 | Finish 10/05/2011 | ||||||
Project Calender: 2 Shifts – Day (6am-6pm) & Night (6pm-6am) | Day 5 | Night 5 | Day 6 | Night 6 | Day 7 | Night 7 | Day 8 | Night 8 | Day 9 | Night 9 | Day 10 | Night 10 |
Activity 1 – Resources Required | F22+F23+R6+R7 | F22+F23+TR3+BM7 | F22+F23+R6+R7 | TR2+BM1 | TR2+BM1 |
| NDT | C1+R6 |
| F3+F4 | F22+F23+R6+R7 |
|
Resource Hours Budgeted | 48hrs (4x12Hrs) | 0 | 48hrs (4x12Hrs) | 24hrs (2x12Hrs) | 24hrs (2x12Hrs) | 0 | 12hrs (1x12Hrs) | 24hrs (2x12Hrs) | 0 | 24hrs (2x12Hrs) | 48hrs (4x12Hrs) | 0 |
Resources Legend: F - Fitter, R - Rigger TR - Trade Person, BM - Boiler Maker, NDT - Non-destructive Testing Team, C – Crane Resources Calender: 1) Day Shift (6am – 6pm) 2) Night Shift (6pm – 6am) |