I have a resource eg rigger working 8 hrs a day(9am to 5pm) for Rs.300/day as standard. I gove him an overtime rate of Rs.90 per hour.
Lets say i have an activity which is planned for one day having this rigger as a resource, the planned cost of the activity is Rs.300.
But if the actual duration is 10 hours (9am to 7pm) then i am strugling to get the right acctual cost displayed for that activity.
Need Help in Understanding the overtime calculations and how should i anter the actual duration or work so that the overtime will be appropiately calculated.