Hi,
I am preparing an entitlement programme for EOT. I have no problem with that as the delay is due to the main contractor delaying their structural work. purely a employer risk event.
I calculated the start variance between their current master programme with the previous one. I add on this variance to my programme date to dovetail their schedule.
Is that the right way to do so ? Also kindly advice what should I write in my transmittal letter to the contractor