After scheduling a project, some bars found out are Discontinuous. The progress (blue bar) stops at data date (time now) and a gap is shown between them with the current bar (remaining work). I was informed by Primavera Australia that the reason a bar is having a gap or a Discontinuous Bar is because of its link/relationship that makes the bar to be pushed thru if it is Finish to Finish relationship. Is this true? In addition, i don't think that is practical to show that the bar should be cut-off and build a gap between a progress and remaining work. It is not good to show in the gantt chart that a bar is a Discontinuous. Can you please advise what actions to be made to show all the bars (in-progress) as Continuous Bars showing their progress and remaining work.
Many thanks.