I've joined a company as a scheduler and their philosophy doesnt make sense to me. They tell me if the activity is completed, relationships doesnt matter. For example, Activity A is predecessor to Activity B with FS relationship and no lags. They say it is ok for activity B to have start and finish dates ahead of those of Activity A, as long as both activities are completed. They do that all over the schedule and always leave the original relationships.
I believe it is wrong to do that even if activities are completed. Can anyone please help me understand why I am right/wrong..
Thanks
Raj