Has anyone had problems when syncing work orders from Maximo to P6, i am having diffcuties when syncing, i get Level Of Efforts (LOE) as a duplicate as well as the activities as a aeperate WBS, Tried deleting and creating a new Porject to elimate corrupt Projects, any help apprecited