Good day,
I built this little schedule, there are only 6 activities, no constraints, everything is pretty much FS, but for some reason the activities are showing up as critical path! When I click on 'schedule' there is an option tab, I have gone in there and changed the Define critical activities and everything is still coming up as critical path!!??!!??!!
Any in-sight would be great!!! Plz & thx :)
Cheers,
Tammy