Dear Friends
i am working in UAE on a construction project , our contract is lump sump project . There are some items in the BOQ under the heading of provisional sum , there are simple concrete jobs whose rate can be taken from main BOQ , however the client is not agreeing on these rates and delete this item( building) from provisional sum and given to some other contractor
Please can some one advice as per UAE Law they have the right for this
your advice will be very helpful to me
Thanks
Best Regards
Umer Mehmood