Hi,
Need help
Problem:
When I have frozen the baseline for the project and release all the constraints, I want to be able to see the variance between my finish milestone vs. finish baseline milestone.
The Finish variance in MSP show a negative number when I have a positive float to the finish milestone, How do you do?
Please help
Regards
Dan