Hi to all expertise
I have a situation like below
Our engineering team sits in a different country, similarly procurement, but I am at site. In P3 ver 3.1, each phase of engineering and procurement is created as separate sub-project. During Monitoring Engineering team updates the sub-project , similarly procurement did the same, since I hold the masterproject, I just pull the sub-project of engineering and procurement through interface to update the master project. This avoids Master project being mishandled by any of the consultant or sub-contractor.
Is there any such process in P6 ver.7, since I am sending the whole master project to all, this make me more transparent to all my consultant and sub-contractor, which I dont want. Can anyone help me
Thanks
Narayanan