Hi Friends,
While updating P6 schedule, i'm trying to enter actuals on finish date upon 100% completion of the activity, but i can't able to update actual date rather which the system responding like "Remain Finish date cannot be earlier than Remain Start date". How to change the Early dates logically? And the predecessor & Successor of this activity has been completed 100% already.
Kindly suggest me to resolve this & explain about how to rectify this logically.
Thanks in advance.
Regards,
Krishna