Dear Friends,
I am working in MEP contractor company in dubai.We got a project in Fujaira which started on oct 2010.It is 18 months project which is to be completed by MAR 2012.Main contractor revised the baseline program & submitted to us. When i reviewed the program, i found that the project has been extended for 3 months.As per contract we got 18 months for the work completion. In this case what we have to do?
Regards,
MOHAMMED SAUD