Dear All,
My program is showing longest path in P6 , with some activties which has a positive float of 135 days also, as well as Zero days float. How could it be possible to generate longest path with positive float and zero float.
Can anybody explain.
regards,
Haresh Jayanth - PMP - Planning Manager