Hello everybody ..I am maaking a Capital Expenditure Schedule linked with the Construction Schedule in Primavera P6..and I am facing the following problems:
1. Salary is getting distributed linearly over the entire activity..now suppose I hire 1 Manager in first month and after two months another 1 but if i load the cost together the entire cost will be distributed evenly.
2. I will buy equipments and payment will be after 180 days how do i impose this delay in expenses...
3. what is the function of Roles and how can i use it in scheduling.
Regards