Hello,
i'm trying to do EVM for a project for the month of November. i filled in the actual hours for all my tasks for the month.....(for all the people), and put zero actuals when that task was not worked on but was scheduled to be worked on.
now, when i'm looking at my "Task sheet", i see the following. (i'm concerned about the second major tasks in bold). I know we're not behind schedule but how can i increase my BCWP to artificially increase my SPI?
BCWS | BCWP | ACWP | SV | CV |
$0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
$60,841.86 | $60,670.96 | $48,947.07 | ($170.89) | $11,723.89 |
$45,791.52 | $38,638.56 | $28,839.89 | ($7,152.96) | $9,798.67 |
$0.00 | $0.00 | $0.00 | $0.00 | $0.00 |