MEP Clearance Delay : Tower Project : Interior Subcontractor
during tender stage a sigle date MEP clearance was given for an entire floor ( A floor is having 30 Rooms \Areas)
Interior Sub Contratcor Submitted a plan based on floor clarance dates taking a certain amount of duration to finish a floor , say 100 days
Actually at site only a small part / clearance was given on the planned MEP clearance date
and after 100 days still several rooms in a floor not cleared for subcontractor
How effectievely this delay can be demonstarted in updated plan were there is no roomwise plan submitted ?
Thanks
Hemant