The contract completion date of our project was already several weeks ago but we haven't finished yet because of several reasons:
1. Our own delay, meaning we haven't finish yet some parts of the work,
2. Client's delay due to late handover of access for some areas, and
3. Addtional works which was issued before the contract completion date but the works will go beyond the contractcompletion date.
My manager ask me to prepare an interim EOT. So anyone have any advice on how to do this considering those items I mentioned above? hanks.