Hello all, I am sorry to start with a question
but i need realy any help, in my problem,
my problem is there is a project for my company in Jordan - death sea, the our contract with the client is (design-build) contract. we are delay because the designer that work with us he is the cause of our delay, this is summary for the problem .I want to depend in my case in temperature to take extension of time from the client put my problem is I don't have the maximum temperature allowable for labor inconstruction site, can you guide me when I can find this temperature ???