All, reference to the forensic claims analysis, it is known that the main basis of the claims shall be refered to the Contract it self as legally binding by both parties.
I've found some EPC contract (particularly in the Lump Sum type of contract) noted that in the Contract Schedule only attached some milestones and put the Delay Liquidated Damages (LD) on the main Milestones such as : Final Acceptance of the works etc..
The schedule which was attached on the Contract document is only showed the WBS until level 2 (High Level schedule)
(Level 0 - Project, level 1 (E,P,C,I) , Level 2 Contract Object / Unit ).
My question is how deep the appropriate WBS to be putted in to the Contract Schedule (levle 2/ 3 or higher) ?
Thanks in advance for your responses....
Alex Iskandar
Indonesia