START Date:
June, 2008 Sishen South Iron Ore Expansion Project (US $400 Million)
Responsible for the developing, monitoring and presenting of the following:
Major Milestone report for the project.
Level 1 Monthly report.
Level 2 Monthly reports.
Level 3 Master schedule for Engineering, Procurement, Manufacturing / Fabrication, Construction & Cold/Wet Commissioning.
Level 4 Engineering schedule (3D modelling).
Level 4 Manufacturing & Fabrication schedules (Incl. ROS dates).
Level 4 Construction schedules for all disciplines.
Level 4-5 Recovery schedules for Engineering, Fabrication & Construction in areas of concern.
Level 4 Cold/Wet Commissioning Schedules (C1-C4)
Tender evaluations & contractual schedules for suppliers and contractors.
Project Trends.
S-Curves for Engineering, Procurement & Construction (measuring the EVP).
Commodity Curves for Engineering, Fabrication & Construction.
Histograms for Engineering, Procurement, Construction & Commissioning.
Histograms for Camp loading.
Resource levelling for the project.
Productivity reports for Engineering (by discipline) & Construction (by contractor).
Minor Milestone report for Engineering & Construction (per discipline).
What-if scenario’s on the Master schedule and on contractor schedules.
Assessment and approval of contractor baseline schedules.
Extension of time assessments on contractor’s schedules.
Forensic claim analysis on schedules.
Progress measurement spreadsheets for Engineering, Fabrication & Construction.
Produce risk analysis schedules.
Responsible for the developing, monitoring and presenting of the following:
Major Milestone report for the project.
Level 1 Monthly report.
Level 2 Monthly reports.
Level 3 Master schedule for Engineering, Procurement, Manufacturing / Fabrication, Construction & Cold/Wet Commissioning.
Level 4 Engineering schedule (3D modelling).
Level 4 Manufacturing & Fabrication schedules (Incl. ROS dates).
Level 4 Construction schedules for all disciplines.
Level 4-5 Recovery schedules for Engineering, Fabrication & Construction in areas of concern.
Level 4 Cold/Wet Commissioning Schedules (C1-C4)
Tender evaluations & contractual schedules for suppliers and contractors.
Project Trends.
S-Curves for Engineering, Procurement & Construction (measuring the EVP).
Commodity Curves for Engineering, Fabrication & Construction.
Histograms for Engineering, Procurement, Construction & Commissioning.
Histograms for Camp loading.
Resource levelling for the project.
Productivity reports for Engineering (by discipline) & Construction (by contractor).
Minor Milestone report for Engineering & Construction (per discipline).
What-if scenario’s on the Master schedule and on contractor schedules.
Assessment and approval of contractor baseline schedules.
Extension of time assessments on contractor’s schedules.
Forensic claim analysis on schedules.
Progress measurement spreadsheets for Engineering, Fabrication & Construction.
Produce risk analysis schedules.