Typically a project will earn the value of major M&E kit according to a series of milestones such as order placed, FAT, delivery & installation. The milestones used and % split of value across them is aligned with the T&Cs of the PO.
But I am curious to know what general rules or guidelines do fellow planners follow when developing inital baseline, before the T&Cs are known? And do these guidelines vary across regions and industries?